Migration of Field Office file servers and DCs to OIT infrastructure.

Description

Thursday 5/26 – Decommissioning of DEP-PH server and DEP-DCPH domain controller (PHEAL LAB)
Friday 5/27 – Monday 5/30 – Data Migration for Nacote Creek File Shares (DEP-GB)
Thursday 6/2 – Decommissioning of DEP-CK file server and DEP-DCNO domain controller (Northern)
Monday 6/13 - Decommissioning of DEP-GB and DEP-DCNC domain controller (Nacote Creek)
Friday 6/24 – Sunday 6/26 – Data Migration of Toms River file shares (DEP-TR)
Friday 7/1 – Monday 7/4 – Data migration of Arctic Parkway file shares (DEP-AP)
Thursday 7/7 – Decomissioning of DEP-TR server and DEP-DCTR domain controller (Toms River)
Friday 7/15 – Decommissioning of DEP-AP2 and DEP-DCAP domain controller (Arctic Parkway)

Project Justification

Required by EO 225

Activity

Kurt Jaegers 5 August 2022, 14:41

Minor delays in the copying of data from Toms River have pushed back the decommission date on TR and Arctic to 8/5/2022