ICIS NPDES - NJEMS Updates for Sewage Overflows - NODE BUILD OUT
Description
Develop Exchange Network Node data flow of NJEMS Sewage Overflow data
Problem Statement
Phase 1 of the project, which involved building an RSP service to receive Sewage Overflow data at DEP, is complete, but it only addresses part of the data flow process that is needed. The next step involves automating the transfer of this data to the EPA. Although manual testing using a CGI test script was successful, automating the process requires utilizing this script and developing a new work plan and project effort by CGI.
In addition, an issue was found with the RSP service allowing unauthorized access to NJDEP's MRF service via "MY WORKSPACE." We need to ensure this is resolved through enhancements to the existing RSP Facility Security Administrator (FSA) functionality
In addition, an issue was found with the RSP service allowing unauthorized access to NJDEP's MRF service via "MY WORKSPACE." We need to ensure this is resolved through enhancements to the existing RSP Facility Security Administrator (FSA) functionality
Project Justification
Required updates to remain consistent with EPA-mandated data system of record and PPG commitments. Automated data flow from DEP to EPA must exist.
https://www.epa.gov/compliance/npdes-ereporting#:~:text=December%2021%2C%202016.-,Phase%202,NOIs)%20under%20a%20general%20permit
https://www.epa.gov/compliance/npdes-ereporting#:~:text=December%2021%2C%202016.-,Phase%202,NOIs)%20under%20a%20general%20permit
Estimated Transactions
None
Target Rollout Date
30 April 2026
Target Rollout Date Reason
None
Linked work items
Activity
Show:
Create issue
Research
Add watchers
Details
Sponsoring Leadership Area
Water Resource Management
Sponsoring Leadership Area's Priority
AP-5
Program Area Lead(s)
Emilie Guzman, Manuel Nolau, Rachel Pepe, Don Hirsch, Anish Rudraraju
DOIT technical lead(s)
Mike Matsko, Aleem Mohamed, Mike Kingkiner
All Involved Leadership Areas
Div. of Information TechnologyWater Resource Management
Created: 13 June 2025, 17:45
Updated:
27 October 2025, 18:32
Draft CGI Work Plan 204 received and being reviewed by DOIT and WQ.