Migration of Field Office file servers and DCs to OIT infrastructure.

Description

Thursday 5/26 – Decommissioning of DEP-PH server and DEP-DCPH domain controller (PHEAL LAB)
Friday 5/27 – Monday 5/30 – Data Migration for Nacote Creek File Shares (DEP-GB)
Thursday 6/2 – Decommissioning of DEP-CK file server and DEP-DCNO domain controller (Northern)
Monday 6/13 - Decommissioning of DEP-GB and DEP-DCNC domain controller (Nacote Creek)
Friday 6/24 – Sunday 6/26 – Data Migration of Toms River file shares (DEP-TR)
Friday 7/1 – Monday 7/4 – Data migration of Arctic Parkway file shares (DEP-AP)
Thursday 7/7 – Decomissioning of DEP-TR server and DEP-DCTR domain controller (Toms River)
Friday 7/15 – Decommissioning of DEP-AP2 and DEP-DCAP domain controller (Arctic Parkway)

Problem Statement

None

Project Justification

Required by EO 225

Estimated Transactions

None

Components

None

Target Rollout Date

None

Target Rollout Date Reason

None

Activity

Kurt Jaegers 5 August 2022, 14:41

Minor delays in the copying of data from Toms River have pushed back the decommission date on TR and Arctic to 8/5/2022