NJEMS Modernization Milestone 6 and 7 Post UAT Enhancements and Bi-directional Flows

Description

Need to enter into work plans with CGI to design, develop, test and rollout MS 6 and MS 7 prioritized enhancements and bi-directional flow. Expected deliverables will be: Bi-directional Flow Guide (Draft and Final), MS 6 and MS7 Enhancements CGI Development Sprints and Internal Testing, JEMT Testing Build, Testing Closeout Build, Release Package (Draft and Final).

Problem Statement

Need to make critical enhancements to the developed NJEMS Milestone 6 (Core Activity Functional Framework) and 7 (Projects) modules before we can rollout these modules into production. In addition we need to develop the bi-directional flow between legacy functionality and modernized Pega functionality to support partial rollout to ensure staff can fully operate while we live in 2 systems.

Project Justification

Functionality needed prior to rollout - See Problem Statement

Estimated Transactions

Not transactional per se

Components

NJEMSPega

Target Rollout Date

28 October 2022

Target Rollout Date Reason

Date base on work plan deliverable schedule and anticipated roll out effort

Linked work items

Activity

james bridgewater 11 January 2025, 03:35

Working on Minimum Viable Product (MVP) issues as part of NJEMS Modernization Completion by 6/2025