ICIS NPDES - NJEMS Updates for Sewage Overflows - NODE BUILD OUT

Description

Develop Exchange Network Node data flow of NJEMS Sewage Overflow data

Problem Statement

Phase 1 of the project, which involved building an RSP service to receive Sewage Overflow data at DEP, is complete, but it only addresses part of the data flow process that is needed. The next step involves automating the transfer of this data to the EPA. Although manual testing using a CGI test script was successful, automating the process requires utilizing this script and developing a new work plan and project effort by CGI.

In addition, an issue was found with the RSP service allowing unauthorized access to NJDEP's MRF service via "MY WORKSPACE." We need to ensure this is resolved through enhancements to the existing RSP Facility Security Administrator (FSA) functionality

Project Justification

Required updates to remain consistent with EPA-mandated data system of record and PPG commitments. Automated data flow from DEP to EPA must exist.

https://www.epa.gov/compliance/npdes-ereporting#:~:text=December%2021%2C%202016.-,Phase%202,NOIs)%20under%20a%20general%20permit

Estimated Transactions

None

Components

NJEMSNODERSP (customized service)/DEP Online

Target Rollout Date

30 April 2026

Target Rollout Date Reason

None

Linked work items

relates to
Issue Type Icon IPTD-484 Air Enforcement data into EPA ICIS system Priority: Medium Assignee:
Idea

Activity

james bridgewater 27 October 2025, 18:32

Draft CGI Work Plan 204 received and being reviewed by DOIT and WQ.

Mike Matsko 17 June 2025, 13:20

Working with CGI to develop the workplan for this effort