Surface Water Treatment Rule (SWTR) Forms
Description
To streamline the collection of surface water treatment rule data specifically turbidity and point of entry chlorine residuals through the development a single entry point (E2 or other) for surface water systems to submit their monthly reports and excel data sets.
Project Justification
The SWTR associated forms are all currently in paper. As part of this project, DWSG is asking to capture full data sets used to produce the summary data. This is an important step for SWTR compliance as it allows the staff to graph data, observe trends, perform qualify control analysis, and identify indicators of poor treatment plant performance.
Attachments
NJDEP WRM Authority Portal - Admin User Guide_v1.0.docx
NJDEP WRM Public Portal - User Guide_v1.0.docx
NJDEP WRM Authority Portal - End User Guide_v1.1.docx
NJDEP WRM Authority Portal - End User Guide_v1.0.docx
DEP Online walkthrough PPT.pptx
WRM Priority Project-CR 01_02_03_20240212_DEP - Signed.pdf
NJDEP_WRM_SWTR_SCD_v3.1_final.docx
NJDEP_WRM_SWTR_FRS_v3.1.docx
NJDEP_WRM_Project_Schedule_20231212 - enfoTech Projects.mpp
NJDEP_Monthly_WRM_Project_Status_Update_20231212 - enfoTech Projects.docx
05.01.2023 RG_AA Comments on NJDEP_WRM_Project_Schedule_FINAL.xlsx
NJDEP_WRM_Project_Schedule_FINAL.xlsx
SWTR DEP IT Project Form.docx
Name
Created at
Size
Actions
FILE
NJDEP_Monthly_WRM_Project_Status_Update_20231212 - enfoTech Projects.docx
2023-12-12 17:18
91.9 KiB
Linked work items
contracting combined with
IPTD-112
eMOR
IPTD-105
Water Quality Parameter Data Solution
IPTD-104
Lead Service Line Inventory Submission and Mapping Application
IPTD-113
ePlanning Tool
Active
Completed
Completed
Active
Activity
Show:
Active
Add watchers
Details
Sponsoring Leadership Area
Water Resource Management
Sponsoring Leadership Area's Priority
AP-11
Program Area Lead(s)
Akinsanya Ode, Joe McNally, Devin Bracey, Amanda Melchiorri
DOIT technical lead(s)
Rich Hyjack, Steve Knapp
All Involved Leadership Areas
Div. of Information TechnologyWater Resource Management
Created: 7 October 2021, 21:10
Updated:
23 April 2025, 12:46
Functional Requirements Specification and System Configuration Design document write-up phases of the project have now concluded. We’ll be entering into the testing phase of the project which is tentatively scheduled to begin mid-February.
Requirements gathering phase completed. SCD Workshop 1 is being scheduled by enfoTech
6/27/2023 - Rich Hyjack initiated the TIP (SAR Process) with NJOIT for the EN Suite Software/infrastructure to be used for this project
Requirement Workshop #2 and #3 scheduled for 7/5/2023 and 8/2/2023
Initial FRS Scheduled for 6/6/2023
FRS Project Schedule Attached
Working on schedule for Functional Requirement Specification (FRS) sessions with enfoTech and WRM
Waiver approved and PO cut for $1,965,120 on 3/7/2023. Jim and Rich will be working with Mike K. and enfoTech to set up initial project planning meetings for projects
Jim B reported final waiver approved by mid December
9/12/2022 - Received design/dev estimates from enfoTech, need to discuss with WRM management before starting the waiver process
Sent to enfoTech on 8/25 for cost estimate along with 4 other WRM Priority projects
considering enfotech
If EnfoTEch and E2, it might use the $2.5mil (would need some investigation).