Migration From Glassfish to TomEE OS
Description
Migrate web app servers from Glassfish to TomEE
Project Justification
Required by NJOIT to migrate off of Glassfish
Activity
Show:
Active
Add watchers
Details
Sponsoring Leadership Area
Div. of Information Technology
Sponsoring Leadership Area's Priority
AP-6
Program Area Lead(s)
James Bridgewater
DOIT technical lead(s)
Rich Hyjack, Victor Aboh, Mike Matsko
All Involved Leadership Areas
Div. of Information Technology
Created: 27 May 2022, 01:47
Updated:
2 October 2025, 19:42
Below is a draft schedule we put together to frame out the evening of 10/10.
Start
End
upgrade
2hr
5:30 PM
7:30 PM
DOIT Test no MyNJ
1hr
7:30 PM
8:30 PM
Program Test no MyNJ
1hr
8:30 PM
9:30 PM
OIT change portal links and DOIT retest
1hr
9:30 PM
10:30 PM
Final Rollout Scheduled for 10/10/2025
Final Rollout schedule being finalized
NODE was moved to TOMEE Production. EIS Flow was tested and working fine. RCRA flow cannot be tested as we are still waiting for a fix from CGI (Devin Freeman has been unsuccessfully working on this for months). We are waiting for vendors to update the new NODE end point on their end so we can test the EN Browser and Radiation Flows.
Issues with E2 in GlassFish have been resolved, so we have been able to do some TOMEE testing week of 12/4/2024. The tests in TOMEE will requires another build for testing the WQP program.
E2, NODE and RSP all upgraded and tested. Waiting for DataMiner Upgrade, presently underway, to be completed before production rollout. Planned production rollout in March 2024