Underground Storage Caverns NJEMS Integration
Description
Develop in house RSP Facility Submittal Services for the following for underground storage cavern permitting: Initial Construction Approval and Initial Operating Permit
Project Justification
New regulations requires NJDEP to regulate new underground storage caverns TCPA related substances
Attachments
Activity
Show:
Completed
Add watchers
Details
Sponsoring Leadership Area
Air, Energy and Materials Sustainability
Sponsoring Leadership Area's Priority
None
Program Area Lead(s)
Paul Komosinsky and Dave Bowman
DOIT technical lead(s)
Nita Mishra, Victor Aboh
All Involved Leadership Areas
Air, Energy and Materials SustainabilityDiv. of Information Technology
Created: 21 July 2022, 19:54
Updated:
10 October 2024, 19:06
tool is up and live in production at DEP Online. As of this comment, Nita Mishra was working to correct a problem with the email notification.
DOIT is finishing up the backend (recently worked with John) and completing the migration setup so as of today we are looking at the dates below for your staff to begin testing:
July 8 – Testing of first service called Initial Construction Approval
July 22- Testing of second service called Initial Operating Permit