Activity

james bridgewater 3 July 2024, 11:38

The Milestone 10 (Phase I & Phase II) and Milestone 11 (Phase I & Phase II)  release package is uploaded to \\ep-fsvr01-hi-e\CGI\NJEMS Modernization\Pre Production Packages\ folder as 20240702_milestone10_milestone11_Pre-Production.zip, see below screen shot. This package is for the Pre-Production deployment (JEMR). Julie and Kurt deploying to JEMR

james bridgewater 11 June 2024, 13:29

Deliverable 5: Milestone 10-11 Phase 1&2 Release Package Final is now uploaded to DEP servers, being reviewed by DBAs

james bridgewater 12 February 2024, 14:22

Work Plan 176 - Milestone 10 Phase 1 & Milestone 11 Phase 1 & 2 UAT signed, testing 3/18/2024 - 4/30/2024

james bridgewater 28 August 2023, 14:56

Work Plan 170 - Milestone 11 Phase I Development signed 8/28/2023

james bridgewater 26 July 2023, 17:09

Heat Map Phase III Comments due to CGI 7/26