Physical Migration of DEP Oracle DB Servers to OIT
Description
Physical migration of DEP Oracle DB servers will be conducted in two phases - Standby database servers will move from Troop C to the hub first, then production servers will move from 401 to the Hub. Mandated by EO 225.
Project Justification
None
Activity
Show:
Completed
Add watchers
Details
Sponsoring Leadership Area
Div. of Information Technology
Sponsoring Leadership Area's Priority
None
Program Area Lead(s)
None
DOIT technical lead(s)
Cleberson Barbosa
All Involved Leadership Areas
Div. of Information Technology
Created: 6 December 2022, 19:32
Updated:
25 May 2023, 15:14
Migration of the standby servers from Troop C to the Hub has been completed on 12/7/2022. Migration of the primary servers will be planned for late January.