Food Waste Recycling Rule RSP Service Pre-Rollout Critical Enhancements
Description
No description
Project Justification
Enhancements needed before original RSP Service can be rolled out into production
Attachments
Linked work items
relates to
IPTD-307
Food Waste Recycling Reporting Rule Data Collection RSP Service
Active
Activity
Show:
Active
Add watchers
Details
Sponsoring Leadership Area
Air, Energy and Materials Sustainability
Sponsoring Leadership Area's Priority
AP-3
Program Area Lead(s)
Jill Aspinwall, Jen Lesniak, Michael Gerchman
DOIT technical lead(s)
Mike Kingkiner
All Involved Leadership Areas
Air, Energy and Materials Sustainability
Created: 22 September 2025, 15:15
Updated:
30 September 2025, 14:39
Dev/UAT covered under CGI Work Plan #201, signed 9/30/2025. Schedule:
Task Name
Duration
Start
Finish
Food Waste Recycling RSP Service Enhancements
50 days
Mon 10/6/25
Wed 12/17/25
Development Sprints
29 days
Mon 10/6/25
Mon 11/17/25
Sprint 1
15 days
Mon 10/6/25
Mon 10/27/25
Development and CGI Testing
11 days
Mon 10/6/25
Tue 10/21/25
Deliverable 1 - Sprint Review & Testing
3 days
Wed 10/22/25
Fri 10/24/25
Sprint 2
15 days
Mon 10/27/25
Mon 11/17/25
Development and CGI Testing
11 days
Mon 10/27/25
Mon 11/10/25
Deliverable 2 - Sprint Review & Testing
3 days
Wed 11/12/25
Fri 11/14/25
UAT
15 days
Mon 11/17/25
Mon 12/8/25
System Testing
5 days
Mon 11/17/25
Fri 11/21/25
Bug Fix
5 days
Mon 11/24/25
Mon 12/1/25
Verification
5 days
Tue 12/2/25
Mon 12/8/25
Deliverable 3 – UAT Close Build
1 day
Tue 12/9/25
Tue 12/9/25
Software Release Package
3 days
Wed 12/10/25
Fri 12/12/25
Deliverable 4 - Software Release Package
3 days
Mon 12/15/25
Wed 12/17/25