Food Waste Recycling Rule RSP Service Pre-Rollout Critical Enhancements
Description
No description
Problem Statement
The Food Waste Recycling Rule Data Collection RSP Service was developed under Work Plan 197, however, there were several out of scope requirements determined during UAT that the program area said they needed to have addressed prior to rollout. Therefore, a separate work plan is needed for the design/development/testing of these enhancements.
Project Justification
Enhancements needed before original RSP Service can be rolled out into production
Estimated Transactions
None
Target Rollout Date
31 October 2025
Target Rollout Date Reason
Rule already final and RSP service needs to go to prod to allow for these e-submissions
Attachments
Linked work items
relates to
IPTD-307
Food Waste Recycling Reporting Rule Data Collection RSP Service
Active
Activity
Show:
Create issue
Active
Add watchers
Details
Sponsoring Leadership Area
Air, Energy and Materials Sustainability
Sponsoring Leadership Area's Priority
AP-3
Program Area Lead(s)
Jill Aspinwall, Jen Lesniak, Michael Gerchman
DOIT technical lead(s)
Mike Kingkiner
All Involved Leadership Areas
Air, Energy and Materials Sustainability
Created: 22 September 2025, 15:15
Updated:
30 September 2025, 14:39
Dev/UAT covered under CGI Work Plan #201, signed 9/30/2025. Schedule:
Task Name
Duration
Start
Finish
Food Waste Recycling RSP Service Enhancements
50 days
Mon 10/6/25
Wed 12/17/25
Development Sprints
29 days
Mon 10/6/25
Mon 11/17/25
Sprint 1
15 days
Mon 10/6/25
Mon 10/27/25
Development and CGI Testing
11 days
Mon 10/6/25
Tue 10/21/25
Deliverable 1 - Sprint Review & Testing
3 days
Wed 10/22/25
Fri 10/24/25
Sprint 2
15 days
Mon 10/27/25
Mon 11/17/25
Development and CGI Testing
11 days
Mon 10/27/25
Mon 11/10/25
Deliverable 2 - Sprint Review & Testing
3 days
Wed 11/12/25
Fri 11/14/25
UAT
15 days
Mon 11/17/25
Mon 12/8/25
System Testing
5 days
Mon 11/17/25
Fri 11/21/25
Bug Fix
5 days
Mon 11/24/25
Mon 12/1/25
Verification
5 days
Tue 12/2/25
Mon 12/8/25
Deliverable 3 – UAT Close Build
1 day
Tue 12/9/25
Tue 12/9/25
Software Release Package
3 days
Wed 12/10/25
Fri 12/12/25
Deliverable 4 - Software Release Package
3 days
Mon 12/15/25
Wed 12/17/25