Smart Inspections (Water)

Description

Cloud/Tablet - based smart inspections from planning to violation and action close out.

Project Justification

Completely mobile platform for maximum efficiency that is enhanced with intelligent tools and robust sources for supporting the evolution of C&E to maximum real-world problem awareness, problem solving and goal achievement, including demonstrated impacts emphasizing EJ and regional, multi-media considerations.

Attachments

Activity

james bridgewater 12 January 2025, 09:38

Tyler’s T3121 Master Agreement was executed earlier this week. The updated SOW for renewal with the new custom agreement number 25-T3121-TYT02 is attached.

Michael McCormack 6 July 2023, 19:14

Water remaining inspection type estimates added. Sunny to meet with Tsuyoshi Nakajima and Darian Capellan in July to discuss high volume inspection types in order to drive use cases to be highlighted in a demo for the Program (WRM) August 1st. TOU still has a lengthy/growing punch list that ARInspect will look to meet on next week.

Pete Tenebruso 1 December 2022, 16:21

Pat has meeting schedule with Carltons group. ARI is putting together plan to estimate cost for remaining water inspection types.

Pete Tenebruso 10 November 2022, 16:40

Mike McCormack is setting up meeting with WRM to look into mapping the WRM inspection types. ARInspect is tasked to develop a plan for all water inspection types.

Knute Jensen 4 October 2022, 17:32

TOU still has significant “punch list” of items from a monthly check in. about half were bugs that will be fixed, half are items that came up previously and may have been decided already, or are changes from previous. Rich to arrange a new meeting with Hastry and Gomez and team that re-sets the table for expectations and possibly sets new more frequent touch points.

Water moving toward enabling individual permits. Leads to look at what is developed which exceeds NJEMS inspection features.

Water General permits - Sam has not seen issues, not aware of issues with others or their progress in testing.

Vivek will confirm/set a planning session for Water. If general and individual are working, what is next?