james bridgewater 30 September 2025, 14:39

Dev/UAT covered under CGI Work Plan #201, signed 9/30/2025. Schedule:

Task Name

Duration

Start

Finish

Food Waste Recycling RSP Service Enhancements

50 days

Mon 10/6/25

Wed 12/17/25

Development Sprints

29 days

Mon 10/6/25

Mon 11/17/25

   Sprint 1

15 days

Mon 10/6/25

Mon 10/27/25

   Development and CGI Testing

11 days

Mon 10/6/25

Tue 10/21/25

   Deliverable 1 - Sprint Review & Testing

3 days

Wed 10/22/25

Fri 10/24/25

   Sprint 2

15 days

Mon 10/27/25

Mon 11/17/25

   Development and CGI Testing

11 days

Mon 10/27/25

Mon 11/10/25

   Deliverable 2 - Sprint Review & Testing

3 days

Wed 11/12/25

Fri 11/14/25

UAT

15 days

Mon 11/17/25

Mon 12/8/25

   System Testing

5 days

Mon 11/17/25

Fri 11/21/25

   Bug Fix

5 days

Mon 11/24/25

Mon 12/1/25

   Verification

5 days

Tue 12/2/25

Mon 12/8/25

Deliverable 3 – UAT Close Build

1 day

Tue 12/9/25

Tue 12/9/25

Software Release Package

3 days

Wed 12/10/25

Fri 12/12/25

Deliverable 4 - Software Release Package

3 days

Mon 12/15/25

Wed 12/17/25