NJEMS Modernization Milestone 11 - All Remaining Screens (Control Documents and Non-Control Documents)

Description

Modernization of NJEMS menu item modules, control document and non-control document windows to Pega

Problem Statement

Need to modernize NJEMS and migrate it to Pega

Project Justification

None

Estimated Transactions

None

Components

NJEMSPega

Target Rollout Date

None

Target Rollout Date Reason

None

Attachments

Activity

james bridgewater 3 July 2024, 11:38

The Milestone 10 (Phase I & Phase II) and Milestone 11 (Phase I & Phase II)  release package is uploaded to \\ep-fsvr01-hi-e\CGI\NJEMS Modernization\Pre Production Packages\ folder as 20240702_milestone10_milestone11_Pre-Production.zip, see below screen shot. This package is for the Pre-Production deployment (JEMR). Julie and Kurt deploying to JEMR

james bridgewater 11 June 2024, 13:29

Deliverable 5: Milestone 10-11 Phase 1&2 Release Package Final is now uploaded to DEP servers, being reviewed by DBAs

james bridgewater 12 February 2024, 14:22

Work Plan 176 - Milestone 10 Phase 1 & Milestone 11 Phase 1 & 2 UAT signed, testing 3/18/2024 - 4/30/2024

james bridgewater 28 August 2023, 14:56

Work Plan 170 - Milestone 11 Phase I Development signed 8/28/2023

james bridgewater 26 July 2023, 17:09

Heat Map Phase III Comments due to CGI 7/26