Wen.Lei 1 July 2025, 14:33

System went “Live” on April 22.

Been troubleshooting and updating a few minor issues post “Go-Live”.

DEP has been troubleshooting the VPN Tunnel for Insight Connection problem with OIT, Motorola, Monmouth County Sheriff's Office Insight Broker. next meeting schedule for Wed 7/2/25

Wen.Lei 10 February 2025, 14:05

“Go Live” Schedule

Knute Jensen (Knute.Jensen@dep.nj.gov) 29 October 2024, 14:15

Go Live now updated to April 25, 2025.  As discussed in semi-annual meeting with DOIT/EM (Harry, Mitzi, Pete, Bob, Knute).   New date provided by Harry.  Pete weighed in on significant effort to expose GIS info into the CAD, and DOIT's role which ends with infrastructure needs while periodic updates fall to 3-part program leads (EM, F&W, Park Police) and/or via vendor.   Harry described 1 to 5-year support from Motorola at $50k/year on the table at last week's meeting.  This is expected to include the GIS updates to the system, with programs doing their part at the data sources.  Sensitive areas designations. etc.     8 new computers are set up manage the CAD and so far working well. 

Wen 12 August 2024, 19:04

On Meeting Aug 7 , Agencies said they were not able to get all the data set and features wanted onto the system on time and would like to push this back to Feb-March 2025 which I also agreed. Having a fully working system is better than having a half done system.

Will supply new date once have schedule.

Wen.Lei 20 February 2024, 14:11

Updated Go Live Schedule

Request Tim K and Neal to find time to remote into MQ Server to get name of software.

Wen.Lei 7 February 2024, 21:32

Motorola Main Meeting was cancelled today by Motorola.

Motorola GIS Discovery and GIS Admin Meeting were held.

  • trying to break down which team is responsible for what between DEP GIS and DEP Agencies GIS Team.

  • Motorola GIS Specialist worked with Ann-Maria to update more data.

  • Motorola did demo of the GIS dataset to give agencies a better understanding of the System.

  • Motorola will schedule a date for GIS Admin training.

Tim K supplied a list of date to discuss the MQ Server, I emailed Kurt the list and waiting for his reply.

  • there was some issue with the current MQ Server, and we would need this new VM for MQ to communicate with the FLEX VM

  • if we plan to use the current ORI, the current IP address/networking will need to move over to the new VM.

    NJ0225400 currently assigned to DEP MQ Server 10.13.6.244.
    “The way my CJIS tables work when it comes to the config for MQ Servers, I can only have one entry using a particular IP address.  If you need to have two connections simultaneously so you can test one without losing your current connectivity, that would require me to establish a "second" server in CJIS with a unique IP, ORI and at least one unique device ORI for testing.”
    - Tara Rockhill

Wen.Lei 22 January 2024, 20:01
  • DEP Agencies request to push the Go Live back as some issues were not resolved by Motorola side.

  • Flex Training is not schedule for May and Go Live is pushed back to June.

  • Redoing the Security Certificate with Michelle, Neal, and Motorola Solutions Architect as it was configured incorrectly last time.

  • Working with Joe, Neal, Tim and Motorola data conversion specialist to convert DEP legacy dataset.

Wen.Lei 21 December 2023, 12:57

because of some unresolved problems with GIS dataset and datatype, along with some problem with the configuration of the Flex system, DEP Agencies would like to prospone the go live date. see email attached

Wen.Lei 7 December 2023, 20:50
  • Motorola GIS still loading GIS Data but have problem with Datatype from certain dataset. He will look into it or contact their engineering department to find a solution.

  • Trying to configure Statelink,

  • Jeff is working with Dave Leitinger on Cradle Point Routers, and GPS now, need to know the network subnet being used.

Wen.Lei 16 November 2023, 20:50

Just escorted 3 days of training for Motorola and DEP Agencies.

Got list of officers from Tim and Joe for the eTickets and eCitation. it was send to Suresh Chennupati at the NJ Court house and they verified the officers; however, we can’t implement it until close to “Go Live” days.

Wen.Lei 9 November 2023, 18:28

Action Items:

DOIT     

  • create SQL DB for Flex, wait for Matt Vroom to give detail Neal and Wen).

DEP GIS Team

GIS Server Configured and installed Spillman software.

Motorola GIS Specialist and GIS Team started GIS Data Integration; however, they are very large files and will need more time to finish. 11/8/23

DEP Agency

  • Retrieve old CAD DB Data (Tim Kasony and Neal)

  • Retrieve old CAD DB Data for CODY Server (Joe Soel and Neal)

Wen.Lei 26 October 2023, 18:32

Updated 11/2/23

  • Updated Schedule

  • Neal and ISU team got the Certificates working for both GIS and Both Linux Server working now, done 11/2/23

  • Angela Updated that Esri and NJ come up with a contract and GIS Team done 10/24/23

  • John and Ann-Maire install the GIS software done 10/27/23

  • Request John and Ann-Marie to have admin right to the GIS Server. done 10/26/23

  • Neal was able to sync the Linux server time. done 10/24/23

  • NOVAA does not have the Hazmat Database around 2008 and suggested:
    “The best option is if your CAD system can use the database in its final release product (CAMEO Chemicals), either as a downloaded app or as a website”, forward that to Matt Vroom (Motorola)

  • will need SSL Cert install on Flex and GIS Servers done 11/2/23

  • NJ STATELINK Tim Kasony, email the info over

  • NJ eCitation. Ask Matt (Motorola) to ahead and contact NJ Courts for NJ eCitation.

  • Matt will need to install some software in the broker server VM to get it to work with Flex. awaiting Office name and Badge ID from Joe Soel

Knute Jensen 23 October 2023, 18:19

Discussion with EM leads (BVF, Mitzi and Harry W.) with Pete and Knute - clarified that the vendor is a first call with support managing the server. DOIT would get a call if vendor identifies a problem in the network. Motorola is the top lead and has 98% of EM market in the US, so responsiveness is expected to be high. Pete confirmed this leadership role in CAD nationally (Spillman/Motorola) via Gartner contacts. Monmouth NJ, Rockland NY and NYC all happy with same. Failures seem to be around poor resource allocations by adopting customers.

Harry: go live expected January.

Wen.Lei 13 October 2023, 12:38

Pending

DOIT

  • create SQL DB for Flex, wait for Matt Vroom to give detail to Neal and I).

  • Retrieve old CAD DB Data (Tim Kasony and Neal)

  • Training begin for Sys Admin, Law and CAD Provisioning

Wen

  • (emailed contact, awaiting response) Need to request Mobile Hazmat Module dataset from directly from NOAA and then Matt can load it onto Flex Server

  • eCrash/ eBrooker server - Spillman admin over at Monmouth County

  • SSL Cert, eTicket, and Statelink

DEP GIS Team - Get GIS Server License quote once State and Ersi is ready.  (needed by end of November)

Agencies GIS  Analysts – gather and submit all necessary types of GIS datasets, boundaries, etc to DEP GIS Team. (In Progress)

Motorola GIS Specialist – When DEP datasets are ready, assist integrating the dataset to the Flex server.

Wen.Lei 5 October 2023, 18:09

DOIT     

  • create SQL DB for Flex, wait for Matt Vroom to give detail Neal and Wen).

  • Retrieve old CAD DB Data (Tim Kasony and Neal)

  • Update the Flex server to 2023.2.15 and Run Patch (working with Matt and Neal on this)

  • Insight Port and SQL Server Port for firewall rules. (Jeff and Maria is setting that up)

  • Test Motorola Client software pending firewall rules update.  (Wen is Working with Motorola Team on this.)

  • Active Directory Integration (waiting for Motorola to help integrate it.)

  • System Provisioning schedule for 10/9/23

 

DEP GIS Team - Get GIS Server License quote once State and Ersi is ready.  (needed by end of November)

Agencies GIS  Analysts – gather and submit all necessary types of GIS datasets, boundaries, etc to DEP GIS Team. (In Progress)

Motorola GIS Specialist – When DEP datasets are ready, assist integrating the dataset to the Flex server.

Wen.Lei 21 September 2023, 12:12
  • Red Hat License Activated

  • Will need to install clients on testing systems before can do the system provisioning on 10/9/23

  • State is still negotiating ESRI contract

  • attached is updated schedule

Wen.Lei 7 September 2023, 20:08

PO for Red Hat License completed, but

“We are still waiting for the licenses for the CAD to show up there, but the PO has been completed. -Kurt”

Wen.Lei 29 August 2023, 13:34
  • Kurt submitted PO for Red Hat License.

  • awaiting for ERIS to finalize contract with NJ for GIS Server License

  • Per Pete’s email, he received a verbal commitment form Steve Matis to fund the needed ESRI licenses

  • Updated System Provisioning and Admin training from Motorola assuming we get the RedHat license on time. (See attached)

  • John and Ann-Marie is getting data from the Programs see below:

Update from BGIS:

  • Heather has reached out to Park Police to get their input on datasets.

  • John and I met with Marie Cook from Forest Fire last week. She is reviewing the information and will be providing feedback on datasets.

Wen.Lei 3 August 2023, 20:18
  • awaiting Ersi to renew contract with state before Angela can get an updated quote for the DEP Agencies.

  • Pete said he will speak to the Assistant Commission for the DEP Agencies on funding the GIS Server License

  • Agencies still haven’t submit GIS data layers to John Fleming. (Motorola Can’t provision the Flex server without the Red Hat License) so expecting more delays.

  • awaiting for Kurt to either use one of our old license or acquire a new one for the Red Hat Server

Without the GIS Server License and the Red Hat License, we can’t go forward with provisioning.

Wen.Lei 25 July 2023, 17:34
  • Awaiting Kurt to acquire or look for an old Red Hat License for the Flex servers. (Motorola Can’t provision the Flex server without the Red Hat License) so expecting more delays.

  • Awaiting to acquire GIS license for the GIS Servers. No PO submitted yet as the Agencies are not sure who will pay for it. GIS Team can’t install the GIS Server Software without the license and Motorola Can’t provision the GIS Server without the GIS Server License) so expecting more delays.

  • also waiting for DEP Agencies to submit data to John Fleming and Ann-Maria to use on the GIS server.

Wen.Lei 13 July 2023, 19:52
  • For Motorola CAD: Dispatcher's work flow meeting, we find out that the agencies are currently not using the GIS part of the system.

  • John Fleming ask agencies to give him GIS data so we can implement it

  • Awaiting Kurt to acquire or look for an old Red Hat License for the Flex servers.

  • Awaiting to acquire GIS license for the GIS Servers. PO should start around after July

  • Need GIS Team to configure the GIS Server once we acquired the license.

  • Request Motorola to Demo the Flex Server and GIS System for us (no reply yet).

Wen.Lei 29 June 2023, 12:12
  • Schedule meeting for Motorola CAD: Dispatcher's work flow using GIS Maps and Point with the GIS Team. 7/11/23 9am

Click here to join the meeting

Meeting ID: 225 190 720 571
Passcode: 6SKexs

Download Teams | Join on the web

Or call in (audio only)

+1 856-338-7074,,814403502#   United States, Camden

Phone Conference ID: 814 403 502#


  • Had the first GIS Discovery meeting on 6/15/23

(To discover how mapping of our GIS data to Motorola’s on the Flex server. Discussed the type of connections needed.)

  • Had first GIS Scope review meeting on 6/28/23 @ 1-3pm

(To Review what Data Layer GeoCoding Data, Point of Interest, Common Places are needed)

Attached is the Scope Review Notes so far.

Action Items for the next GIS Scope meeting:

Motorola GIS Team:

Please send the document over so DEP can add additional/missing items to it. (see attached)

DEP Agencies:

Please go over that document and add additional/missing items if needed.

DOIT GIS Team and DEP Agencies GIS specialist:

Please go over existing data model and new dataset to be implemented. (Will take a few weeks).

Once that is done, please let me know so I could schedule for the next meeting

Wen.Lei 15 June 2023, 16:48
  • Scheduled GIS Discovery meeting for Motorola CAD on 6/15/23 @ 2:30-3:30pm

  • Awaiting for answer from Motorola to see if we can start provision the Flex servers without the Red Hat license activiated first. If we can’t start, then we need to wait until next fiscal period for DOIT to acquire the Red Hat license (Around August) before we can begin.

  • Joe said their programs will pay for the GIS License after July 1st. He’ll send me the account numbers from all the programs.  It should be split evenly 3 ways.

  • Updated Motorola schedule is attached:

Wen.Lei 1 June 2023, 20:08
  • OIT Reassign IP for one of the Flex Server to prevent IP Conflict with the ArgGIS Server.

  • Kurt and us decided to get one Flex server up and running first and work on the passive fail over later.

  • Kurt said he will work on updating the Flex server time, Linux licensing, and will act as an escort to OIT server for Motorola to provision the Flex server.

  • Submitted Privilege Escalation form to Pete from Solution 2, Joe Soel’s group, Harry Wertz’s group, and GIS Team. (awaiting form from Tim Kisony)

  • Scheduled 6/9/23 for DEP GIS Team and Motorola GIS Team to further discuss implementation.

  • Waiting for David Golden and Pete to discuss the cost of the GIS License for the Server and maintanence package.

  • Dave Leitinger said he had a conference call with Gary Maholic who own NetMotion for 2 years and Gary is planning to abandon Netmotion and try a new approach. Wait and see new approach work.

  • Dave L had a conversation with Joe Soell about it.

Wen.Lei 24 May 2023, 12:30

5/23/23

IP Conflict between Flex2 and one of the GIS server, requested change. (5/24/23 got notice from OIT that it was changed) submit need build info.

5/24/23

resend OIT’s Privilege Escalation Access form to DEP agencies and Solution2,

Wen.Lei 18 May 2023, 17:58

5/11 send OIT’s Privilege Escalation Access form to DEP agencies and Solution2, haven’t received any back yet.

Will have a meeting on 5/19 11am with Motorola, DEP Agencies, Solution2, and DOIT to iron out any detail to get the system rolling.

Click here to join the meeting

Wen.Lei 3 May 2023, 20:10

Veronica (OIT) reply back today with the updated IP.

I emailed Motorola and Pete to sign the Privilege Escalation form. (All signed)

I updated Service Now Request number RITM0087512 with the new signed form.

I also email Veronica (OIT) the form.

Ask Jeff if he were about to install security software on the Flex (Linux) server.

Ask Larry about joining GIS systems to DEP domain.

Email Solution 2 the Privilege Escalation form. (Awaiting reply)

Follow ups and To Do:

after the above is done. we can let Motorola remote in and implement their part.

scheduled meeting with the DEP agencies, Motorola and Solutions II (Monday 8, 2023).

Need to know GIS Licensing status, will have a meeting with Pete on May 9th 2023.

Install GIS Software on the 2 GIS Server.

Jeff will submit Firewall form

Email Solution 2 the Privilege Escalation form. (Awaiting reply)

Wen.Lei 2 May 2023, 20:53

Email Veronica about status of IP subnet change 5/1/23, no reply yet.

Wen.Lei 20 April 2023, 20:33

Update 2:

  • Pete signed the form. I created a ticket with OIT and submitted the forms. Request Number: REQ0085713

  • Email OIT-PMG@tech.nj.gov the “Play book”. list of contacts.

  • asking “Solution II” question regarding the VM build before submitting to OIT.

Wen.Lei 20 April 2023, 19:15

Update:

  • Motorola finally signed all the forms. Windows Server was check instead of Linux but Veronica from OIT said it’s ok if I include a note on the ticket.

  • Forward the forms to Pete and Kurt for signing.

  • Had a meeting with “Solution2” and the agencies on Tuesday 4/17/23 and talk about Client Overview, Ticket Generation, (Scope of Work, Out of Scope, Client Responsibilities, Description of Services, Reports and Frequency Table)

  • they will require a Windows Server virtual machine called “monitoring collector”. It will require at least 2 vCPU, 2GB of free memory and 75GB of free storage. I will submit a ticket with OIT for it.

  • They will remote (with the oversight of DEP agency) into this machine to access flex servers for updates and maintenance.

Wen.Lei 20 April 2023, 12:19

4/17/23

Veronica from OIT replied back the IP change is moving through the workflow and will let me know once it's completed

4/20/23

  • email Motorola again asking for their supervisor’s signature for the OIT forms. This is after a couple of emails to them (4/6/23, 3/23/23, without any reply from them. I email them again today including Pete and Kurt on it.

  • Will have a meeting with Pete and team to discuss progress and GIS Server (date TBD)

Wen.Lei 6 April 2023, 16:50
  • OIT Loaded the Linux Image; however, they assign the two Linux system with subnet Address that DEP couldn’t access.

  • Requesting OIT to change it to one that DEP can access to 10.13.0.0/16 or 10.19.0.0/16. Email Veronica on 3/29/23. haven’t heard back from her. emailed her again today 4/6/23.

  • Once the above is done, Jeff Martin can install our security software on them.

  • Motorola still haven’t sign the Supervisor portion of the OIT forms. just email Jessica Coker again 4/6/23.

Wen.Lei 23 March 2023, 13:14
  • Find out from OIT Motorola send Windows OVA instead of Linux and have to redo the image.

  • Requested Linux one from Motorola.

  • OIT updated server with Linux OS and finish putting the Linux OS up; however, Motorola didn’t supply any Linux credential so we couldn’t access it and the contact from Motorola is out until 3/27/23.

  • Also email Motorola Project manager for Admin credential, awaiting reply.

  • The two GIS servers and the eCrush server is up. Jeff is installing required security software onto it.

  • Also awaiting for Motorola to finish signing OIT Server access form.

Wen.Lei 28 February 2023, 14:34

Need to submit a few forms.

From: Ortiz, Veronica [OIT] <Veronica.Ortiz@tech.nj.gov>
Sent: Tuesday, February 28, 2023 9:29 AM
To: Lei, Wen [DEP] <Wen.Lei@dep.nj.gov>
Subject: DEP - Motorola Flex CAD System

 

Hello Wen,

 

The server build for the Motorola Flex servers has been entered into the system. The Privilege Escalation form needs to be completed by an admin who needs access to the servers. The Playbook needs to be completed so ESD knows who to contact after hours. I added the FW form just in case you need it and the server build to help complete the documents. Please submit the documents to the designated email address listed on the forms. Let me know if you have any questions.

 

The build is now pending the DNS team in ServiceNow.

Wen.Lei 21 February 2023, 20:21

Veronica Ortiz from OIT said the VM build is almost complete, just waiting for the IPs to move forward.

she wanted to know if we have a DEP Admin group contact and who will install SQL Express.

Barbara emailed me the updated diagram for this project. will update it.

Wen.Lei 31 January 2023, 13:10
  • Neal said he can see where the legacy data reside but can’t access it or see its size. I ask Tim K to coordinate a meeting with Central Square (Vendor) and Neal on how to access their database.

  • Email OIT if they can get the VM Servers up and running first so we can go on with the CAD software Install and circle back to pointing where the legacy database will be while Neal is working with Central Square. [Awaiting reply]

  • Got updated Quote from Angela W for GIS Server and GIS Desktop Advanced Concurrent.

ArcGIS GIS Server Standard Up to 4 Cores Perpetual License $18,135.00

1 ArcGIS Desktop Advanced Concurrent Use Perpetual License $11,425.00

  • Sticking point: Agencies said previous management said we might able pay for the license for the GIS Server and GIS Desktop Advanced Concurrent and said they don’t have the budget for it; however, I spoke to previous management and said that is not the case as the agencies are the one who’s using the system and not DOIT related.

Wen.Lei 17 January 2023, 19:10

Submitted Server VM request to OIT. 11/22/22

waiting for Tim to submit database size for legacy SQL Server. Neal will need that to see which SQL server to have the space to store that data.

OIT will need to know which SQL Server to point to for legacy data and they can’t proceed before that.

“Motorola’s Solution 2” is waiting in DOIT Procurement. Solution 2 is for configuring and Supporting of the CAD System.

Wen.Lei 14 November 2022, 14:14

Updated CAD_ARCHITECTURE Diagram with eCrash Broker Server

Updated List of Action Items.

Wen.Lei 14 November 2022, 14:13

To be built at HUB:

 

  1. A Flex server, which is a combo web-app-DB deployed via .ova file. The FairCom DB is built-in. This will be RHEL.

 

  1. An ArcGIS server for geographic data. DEP will provide the license.

 

  1. A broker server for eCrash/eCitation Lexis Nexis service.

 

  1. A stand-alone MySQL server for legacy data (DEP to determine if this is necessary)

 

 

To be built at HAM:

 

  1. A Flex server, which is a combo web-app-DB deployed via .ova file. The FairCom DB is built-in. This will be RHEL.

 

  1. An ArcGIS server for geographic data. DEP will provide the license.

 

 

Integrations with other systems, internal or external:

Rapid Notification - would use state email gateway, needs web access for email content/creation  (DEP to determine if this is necessary)

VESTA - suite of messaging tools that includes an SMS gateway  (DEP to determine if this is necessary)

Access to the Monmouth County's Insight server

NetMotion VPN will be used by DEP officers on the road - Check with Pete Tenebruso for procurement status

BeyondTrust's Bomgar remote access tool will be used by Motorola for escorted maintenance

Operators are co-located with NJSP at Negron Drive in Hamilton

 

High-availability/DR

There is no auto-failover. In a situation where the primary site was unavailable, backups would be manually restored to the Flex DB at the secondary site to allow its use.

 

Question for DEP - How will operators and officers authenticate to the system? Active Directory or ?

 

Action Items

DEP to determine where the legacy data are, and make decision regarding location of the data for the new system, i.e., a new DB server, or an existing location.

 

DEP to determine if they will use either Rapid Notification or VESTA options.

 

DEP to inquire with Pete Tenebruso about status of NetMotion VPN for officer use.

 

Motorola to send specs for broker server to DEP, for Capacity Planning's use.

Wen.Lei 13 October 2022, 20:05

Motorola notified me their Applications Specialist (Robert) will be conducting an onsite Business Process Review on Oct 25, 26, and 27th with Joe Soell, Tim Kasony, and Harry Wertz to discuss their processes.

Wen.Lei 13 October 2022, 19:51

Submitted New Architect Diagram to Barbara (OIT) OIT.SolutionsArchitecture@oit.nj.gov

Wen.Lei 12 October 2022, 13:54

Updated Architect Diagram from Ted

Knute Jensen 26 September 2022, 17:06

Already purchased, Wen hasn’t begun installation and is getting info and guidance on doing that. Last met to schedule some training. Need to copy VM. Won’t go live for at least a year. Joe meeting with Motorola twice through Oct. NJDEP did a SAR on this already. Wen has lead on install. We need more clarity on roles for maintenance, support, who to call first in breakdowns, etc. Wen and Joe to meet this week on next steps.

Ted.Atogwe 1 July 2022, 15:23

Project is now in planning phase. NJDEP is waiting for the vendor to assign a manufacturer implementation manager. Once that is done, resource allocation will begin, and project implementation plan/schedule will be drafted.

Ted.Atogwe 1 July 2022, 15:21

Purchase order (PO) # 83909:440 was sent to the vendor directly by Grace Barger via NJSTART and was confirmed by email (screenshot attached) on Wednesday 6/29/2022